Location
  • San Marcos, TX
Services Provided
  • Civil

Project Case Study

San Marcos Fire Station


The project scope was comprised of the 11,000 square foot, two-story fire station. Civil design services included a 6,500 cubic foot above ground storm water detention facility and new sidewalk with ADA barrier free curb ramps. Also included was 120 LF of 6 in fire line, 120 LF of 6 in water main and new hydrants and 600 LF of 6 in sanitary sewer. The superstructure consisted primarily of wood framing with CMU walls framing the perimeter of the apparatus bays and steel frames above the apparatus bay doors and at the entry tower.